Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

French fries to juicy tomatoes, rock art brings joy to walkers in Victoria

James Bay yard filled with painted rocks delights all ages

‘Depression-era’ unemployment figures could hit Greater Victoria

South Island Prosperity Project launches new dashboard to measure effects of COVID-19

Langford bartender hosts singalong livestream for seniors

Live Senior Singalong takes place daily at 1 p.m. on Facebook

Langford woman frustrated over visitor restrictions to see 96-year-old mother

Island Health to introduce virtual visits at long-term care facilities

Shot fired through young family’s home in Victoria, man in custody

No injuries reported from incident in 1200-block of Yates Street

LIVE: Procession to honour Snowbirds Capt. Jennifer Casey comes to Halifax

Snowbirds service member died in a crash in Kamloops one week ago

One man dead after standoff with Chilliwack RCMP

The Independent Investigations Office of B.C. is investigating the RCMP’s role in the death

B.C. employers worry about safety, cash flow, second wave in COVID-19 restart

A survey found 75 per cent of businesses worry about attracting customers

Facing changes together: Your community, your journalists

The COVID-19 pandemic has changed the world in ways that would have… Continue reading

Ex-BC Greens leader Andrew Weaver says province came close to early election

Disagreement centred on the LNG Canada project in northern B.C.

Canada’s NHL teams offer options to season-ticket holders

Canadian teams are offering refunds, but also are pushing a number of incentives to let them keep the money

B.C. premier says lessons to learn from past racism during response to pandemic

B.C. formally apologized in the legislature chamber in 2008 for its role in the Komagata Maru tragedy

Snowbirds to remain at Kamloops Airport indefinitely after fatal crash

small contingent of the Snowbirds team is staying in Kamloops, acting as stewards of the jets

82% of all test-positive COVID-19 cases in B.C. have recovered

B.C. had 303 active cases as of Saturday, May 23

Most Read