Liberals’ 2-year infrastructure plan set to take 5: documents

Government says 793 projects totalling $1.8 billion in federal funds have been granted extensions

Late last year, officials warned that a federal spending spree to repair crumbling roads and water systems could take three years longer than expected to complete, based on internal documents outlining issues with the first tranche of cash in the federal government’s infrastructure program.

The federal government had originally hoped to have cities and provinces complete $5.4 billion in transit and water system work by this March, but quickly realized that more time was needed.

A “secret” fall briefing note to Infrastructure Minister Amarjeet Sohi, obtained by The Canadian Press through the Access to Information Act, says delays hampered a large number of construction projects, requiring that the deadline be extended as far as March 2021.

The heavily blacked-out document predicted the majority of water and transit projects “would require extensions not only for a third year, but beyond into a fourth year (i.e. 2019-20) and fifth year (i.e. 2020-21),” referencing the federal fiscal years in brackets.

Sohi agreed to a blanket deadline extension to March 2020, turning what was to be a two-year stimulus program into a four-year plan.

He said the decision to grant extra time to 2020, instead of 2021, was based on the expected cash flow for projects and the ability for construction companies to handle all the extra work.

“This is not about that projects are being delayed, it’s about taking a little longer to complete those projects or taking a little longer to have the buses manufactured because of construction and manufacturing capacity,” Sohi said in an interview from Edmonton.

“From our perspective, we made a commitment to build and rebuild infrastructure and focus on the repairs in phase 1 and … we are achieving the results we intended to achieve, but we also want to give flexibility.”

As of Friday, the federal government had approved more than 3,400 water and transit projects with a combined federal contribution valued at almost $4.2 billion. Of that money, federal coffers had only doled out about $175.6 million to date, based on figures available on the Infrastructure Canada website.

Federal dollars flow once cities and provinces submit receipts for reimbursement, often creating a lag between when work takes place and when the federal money is spent.

In some cases, the federal government won’t receive receipts until a project is completely done. In other cases, projects are delayed because of labour strife, bad weather or other factors beyond Ottawa’s control.

The government says 793 projects representing about $1.8 billion in federal contributions have been granted individual extensions from Sohi. Between those extensions, and delays in filing expense claims, federal officials last year decided to shift more than $2 billion in planned spending to future years.

Provincial and municipal officials say that the time needed to go through the funding approval process contributed to the delays.

Having officials vet the details of each proposal before getting federal approval for funding meant some cities put off breaking ground until they knew federal funding would come their way.

“We heard loud and clear from some municipalities that they were struggling to meet two pieces of criteria: timeline requirements and a provision that would require municipalities to incur 60 per cent of their costs by March 31st, 2018,” said Alex Benac, a spokesman for Ontario Infrastructure Minister Bob Chiarelli.

The extra time and removal of the local spending requirement, which Chiarelli asked for in September, has given cities “much-needed time to get shovels in the ground and keep their projects on track according to a more generous, achievable timeline,” Benac said.

Federal and provincial officials say the lessons learned from the first phase of the program will be used in designing the second phase.

Both sides want funding agreements for the second, longer and more lucrative phase of infrastructure spending signed by March.

Jordan Press, The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

VIDEO: Tent city moves to Woodwynn Farm, arrests made

The group is asking the government to provide housing for 60 tent city members

Cougar spotted Saturday morning in Saanich

Police found paw prints consistent with cougars in the area

Saanich passenger caught smoking weed in a car issued $230 fine

Saanich police did a field sobriety test on the driver and deemed it safe for him to drive

B.C. Guide dogs is looking for volunteer puppy raisers

Labrador retrievers need to learn obedience and socialization before heading to work

Colwood Elementary gets new inclusive and accessible playground equipment

Parks and playgrounds on the West Shore have equipment for everyone

WATCH: Twelve Angry Jurors puts a new spin on an old tale

Canadian College of Performing Arts opens season with reworked version of Reginald Rose teleplay

Crime Stoppers most wanted for Greater Victoria for Oct. 19

Greater Victoria Crime Stoppers is seeking the public’s help in locating the… Continue reading

POLL: Do you support amalgamation for communities in the Capital Region?

Residents in Victoria and Saanich will be voting on Oct. 20 on… Continue reading

Team Canada gold medal winners for first time in world curling championship

Team Canada earned gold in Kelowna at the 2018 Winn Rentals World Mixed Curling Championship

Payette invites critics to ‘come and spend a few days’ with her

Governor General Julie Payette made her first official to B.C. back in March

More pot stores expected in B.C. in coming ‘weeks and months’: attorney general

Attorney General David Eby and Public Safety Minister Mike Farnworth visited the new BC Cannabis Store in the province’s Interior

Telus launches charitable foundation to help vulnerable youth

The Telus Friendly Future Foundation complements other social initiatives by the company, including Mobility for Good

Police say suspicious death of B.C. artist ruled a homicide

Patrick Zube Aylward’s body was found in a residence on a rural road outside of Seton Portage, west of Lillooet, B.C.

Temporary roads being built in areas affected by landslide in northern B.C.

Emergency Management BC news release says Disaster Financial Assistance is available to eligible residents of the Peace River Regional District who may have been affected by the landslides

Most Read