$16-million price jump forces Victoria council to rethink bridge project

Council to be given three price and build options for proceeding with new Johnson Street Bridge

Ten days after Victorians learned they’d received an extra $16.5-million federal grant for the Johnson Street Bridge replacement, the cost of the project rose by approximately the same amount.

The estimated price has jumped from $77 million to $92.8 million.

Victoria Mayor Dean Fortin called the revised budget “surprising, and frustrating and disappointing.”

“It’s lost opportunity on the funding we received from the federal government,” he said.

Proceeding as planned, however, isn’t city council’s only choice.

“Council is faced with a big decision and not one that I anticipated having to put before them,” said city manager Gail Stephens.

On the table are three options.

The first: to hire a contractor to build the bridge at the higher cost estimate.

The second: to hire a design-construction team with instructions to keep the same bridge functions, but alter the architectural design as needed to save cost.

The third: to stick to the original $77-million price tag by altering both the function and design of the bridge to meet this budget. This could mean narrowing the bridge by removing bike lanes or a sidewalk.

On Tuesday, all the project executives met with the News to outline their pitch for option one.

“With the additional federal funding … we can complete the bridge with no tax increase to citizens and no tax increase to business,” said city manager Gail Stephens.

The waterfront is one of Victoria’s most important assets, she said. “Often a bridge is used to revitalize an area … They tend to spur new development and new tourism.”

Added bridge architect, Sebastien Ricard, “It’s about trying to create a destination, something that is an attractor.”

Some on council, however, were not convinced by the need to stick to the original plan.

“Our email in-boxes are beginning to fill,” said Coun. Lisa Helps in an email to the News, hours after the news broke.

“One person just wrote and said to all of us, ‘I beg you, please do not stray from the original design intent.’ I simply replied with ‘At what cost?'”

Unlike the mayor, Helps said she was not surprised to get the news.

“This is precisely the kind of situation councillors (Ben) Isitt, (Shellie) Gudgeon and I were trying to avoid when we voted in favour on (Feb. 16) of going back to the drawing table and designing a simpler, more cost-effective bridge. That motion failed and now here we are a month later with a similar option outlined in a staff report.”

Council is scheduled to debate the options tomorrow (March 15).

The biggest question facing them is: How much money could be saved by sacrificing design and function?

According to the city, the answer is not much.

“We priced out a plain-jane bridge and the difference in the hard construction number between that and the iconic structure that we’ve designed is about $6 million,” said Joost Meyboom, of MMM Group. Those savings evaporate due to other expenses related to changing course, he said.

Options 2 and 3 also present costly risks, argued Stephens.

Changing the project’s scope could prolong the process, putting a risk the target deadline of 2016, upon which a $21-million federal grant depends.

It could also invalidate the results of November 2010 referendum, when a majority of voters approved a borrowing bylaw to build a bridge with a certain look and set of amenities. Building even a somewhat different bridge could require the city to go back to voters for permission to proceed.

Bridge project critic Ross Crockford questioned the timing of the announcement.

“When did these things start becoming apparent to staff?” he asked. “Did they wait until the point of no return (after the rail bridge was demolished) to unleash upon council and the public that it’s going to be all this extra money?”

Meyboom, however, said the refined number crunching “has settled down in the last week of two.”

rholmen@vicnews.com

Just Posted

Saanich Mayor says ‘no costs asked of municipality’ for proposed film studio

Mayor Fred Haynes made that comment after questions from watchdog group

RCMP confirm foul play in death of 60-year-old Metchosin man

Police believe crime an isolated incident

Researchers head out from Sidney to explore Canada’s largest underwater volcano

The Explorer Seamount is as large as Greater Vancouver and full of previously undiscovered species

Police seek witnesses after man assaulted at Central Saanich bus stop

Man found Saturday on Keating X Road remains in serious condition at Victoria General Hospital

RCMP identify Sidney bank robbery suspect, believe he is still on Vancouver Island

Warrant issued for arrest of North Vancouver man for TD Bank robbery

VIDEO: Dashcam video captures moment Victoria cyclist struck

Police seeking cyclist captured in video

UPDATE: Youth seen with gun at Nanaimo mall, suspect now in custody

Woodgrove Centre shut down during police incident

B.C. man dies from rabies after contact with Vancouver Island bat

Last known case of human rabies in B.C. was 16 years ago

Crown recommends up to two-year jail term for former Bountiful leader

Crown says sentence range should be 18 months to two years for Bountiful child removal case

VIDEO: Wolf spotted swimming ashore on northern Vancouver Island

Island wolf population estimated at under 150 in 2008, says VI-Wilds

Diversity a Canadian strength, Trudeau says of Trump tweets at congresswomen

Trudeau avoided using Trump’s name when he was asked about the president’s Twitter comments

Garneau ‘disappointed’ in airlines’ move against new passenger bill of rights

New rules codified compensation for lost luggage, overbooked flights

Canadian is detained in China on drug allegations: Chinese government

Detention of a Canadian in China comes as part a diplomatic dispute triggered by arrest of Huawei exec Meng Wanzhou

Rare white ravens spotted again in mid-Island

Nature photographer Mike Yip said mysterious birds back in Coombs area

Most Read