Anti-smart meter protester Sharon Noble greets delegates at B.C.'s 2012 municipal convention in downtown Vancouver. Wireless meters have been blamed for bee deaths

B.C. smart meters cleared in Ontario debacle

$1 billion over budget, Ontario tried to use smart grid to shift load to off-peak hours. It hasn't worked

Ontario has become notorious for bad energy policy decisions, from leaky nuclear plants and brownouts, to a costly green energy subsidy deal with Samsung, to a pair of hastily cancelled gas-fired power plants that helped push former premier Dalton McGuinty from office.

So it was no surprise to weary Ontario electricity ratepayers when Auditor General Bonnie Lysyk wrapped up 2014 with a report condemning the province’s wireless smart meter program for a $1 billion cost overrun and failure to reach the program’s goal of reducing power consumption.

Unlike BC Hydro’s wireless meter program, Ontario used the smart grid’s real-time consumption data to offer discounts for off-peak power consumption, hoping to ease the load on its outdated power grid while giving customers some relief from soaring rates. But few embraced the incentive to run their clothes dryers late at night to save money.

Diehard smart meter opponents in B.C. jumped at the bad news from Ontario. Their theories of sudden billing surges, vague health concerns and even smart meter surveillance have all been debunked, but here they had a credible voice saying they are a waste of money.

Alas for them, Lysyk held up B.C.’s smart meter program as the model Ontario should have followed.

The Ontario government “did not complete any cost-benefit analysis or business case prior to making the decision to mandate the installation of smart meters,” the auditor wrote. “This is in contrast to other jurisdictions, including British Columbia, Germany, Britain and Australia, all of which assessed the cost-effectiveness and feasibility of their smart metering programs.”

Lysyk’s report also noted BC Hydro developed its business case in 2006, updated it in 2010 as meter technology evolved, and implemented it in 2011 with a plan to recover costs over 20 years. BC Hydro’s savings come mainly from reduced electricity theft, faster location of power outages and more accurate load management.

B.C. also responded to the anti-smart meter holdouts with an optional fee to cover manual meter readings for those who insisted the cellphone-like data transmissions are a threat to their health.

 

Just Posted

Saanich councillor slams McKenzie Interchange Project

Coun. Judy Brownoff said the project will only create more greenhouses gases and traffic

Oak Bay father charged with double murder takes the stand

Andrew Berry pleaded not guilty to the December 2017 deaths of his two daughters

Victoria contractors file civil claims for work on Sooke Tim Hortons, Petro Canada

Contractors file civil suits against Petromaxx, T’Sou-ke First Nation

Both suspects arrested from Oak Bay armed robbery

Perpetrators allegedly used a firearm to rob Oak Bay Avenue resident

VIDEO: Title of 25th Bond movie is ‘No Time to Die’

The film is set to be released in April 2020

Greater Victoria wanted list for the week of Aug. 23

Greater Victoria Crime Stoppers is seeking the public’s help in locating the… Continue reading

POLL: Should there be a ban on gas-powered leaf blowers?

We’ve all heard them, and most likely cursed them under our breath.… Continue reading

‘Unsubstantiated’ bomb threat against CP Rail in Revelstoke

On Aug. 18, a bomb threat was made against CP Rail in Revelstoke

Coroner’s inquest into fatal police shooting in Port Hardy begins in Campbell River

James Reginald Butters, 24, killed in 2015 after RCMP responded to call of male uttering threats

New ‘Matrix’ film set with Keanu Reeves and Lana Wachowski

Fourth installment to feature Reeves as Neo and Carrie-Anne Moss as Trinity

Catholic church buys $7.5M equestrian facility in B.C., plans ‘agri-retreat’ centre

Church hopes to grow crops, host students and others on Bradner property

New regulations require training for B.C. addiction recovery homes

Inspections, standards replace ‘wild west,’ Judy Darcy says

Trans Mountain gives contractors 30 days to get workers, supplies ready for pipeline

Crown corporation believes the expansion project could be in service by mid-2022

Most Read