Craigflower Bridge construction delayed until 2013

Environmental, archaeological permits still needed before builders can be hired

Plans to build the new Craigflower Bridge have been put on hold untill next year, after municipal engineers couldn’t achieve everything required in the tight timeframe they had.

Jim Hemstock, Saanich’s manager of transportation, said the initial plan to begin construction on June 1 was aggressive. Now it’s considered unachievable.

“There are environmental and archaeological processes (still outstanding) that are long and complicated,” he said.

Last week, staff decided the project would be delayed by either six months or one year.

“We’re still considering the pros and cons of summer and winter building,” Hemstock said. “We know that the two big drivers that effect the public would be Christmas shopping and getting kids to school.”

From the engineering side of things, however, the delays are more complicated.

Saanich and View Royal share responsibility for the bridge. Both municipalities need to ensure construction doesn’t impact the salmon or herons that call the Gorge Waterway home.

Archaeologically, two different permits are required to build on the sensitive lands near the historic Craigflower schoolhouse on the Saanich side, a former native burial ground.

“We don’t have the permits. … Putting (the project out for tenders) now, not knowing if you can proceed is not a fiscally responsible things to do,” Mayor Frank Leonard said. “Uncertainty usually leads to higher prices. … It’s better we spend taxpayers’ money wisely and do it a bit later, than rush to get it done.”

An announcement on whether bridge construction will begin in January 2013 or July 2013 isn’t expected to be made until August.

The $10.7-million Craigflower Bridge reconstruction project is funded mostly by federal gas tax money. The existing narrow, two-lane bridge is 79 year old. It’s slated to be replaced by a three-lane bridge, complete with bike lanes and wide sidewalks.

kslavin@saanichnews.com

 

Just Posted

Processed sewage is still being deposited at the Hartland landfill rather than sent as biosolids to a Richmond cement plant. (Black Press Media file photo)
Biosolids at Hartland still being placed on landfill in Saanich

Richmond cement plant up and running, but CRD end product not suitable for purpose

An SUV sits where it crashed through the front window of the 2:18 Run store in Fairfield Plaza, after the driver appeared to lose control on Monday afternoon. (Photo by Phil Nicholls)
Driver crashes through front window of Victoria running store in Fairfield

Phil Nicholls of 2:18 Run said crash sounded like an earthquake at first

Elk Lake Drive area resident Michael Blayney protests a proposed multi-building development for his Royal Oak neighbourhood, outside Saanich municipal hall on Monday (June 14). (Photo by Megan Atkins-Baker/News Staff)
Demonstrators protest 11-storey development on Elk Lake Drive in Saanich

Saanich locals gather at municipal hall to protest development, public hearing goes Tuesday

Seismic upgrading and expansion work at Victoria High School is about a year behind due to pandemic-related factors, the Greater Victoria School District announced. (Photo by Cole Descoteau)
Victoria High School seismic work, expansion a year behind schedule

Greater Victoria School District now targeting September 2023 for reopening of historic school

The Greater Victoria Harbour Authority is calling on Transport Canada to rescind its ban to Feb. 28, 2022 on cruise ship stops in Canada, to allow planning to begin in advance of a reopening of the cruise industry next year.
Greater Victoria Harbour Authority seeks end to federal ban on cruise ship stops in Canada

Greater Victoria Harbour Authority CEO hopes cruises will resume by 2022

Canadian Prime Minister Justin Trudeau participates in a plenary session at the G7 Summit in Carbis Bay, England on Friday June 11, 2021. THE CANADIAN PRESS/Adrian Wyld
Canada donating 13M surplus COVID-19 vaccine doses to poor countries

Trudeau says the government will pay for 87 million shots to be distributed to poor countries

Kelowna-Lake Country MLA Norm Letnick, assistant deputy speaker at the B.C. legislature, presides over committee discussions. The legislature is completing its delayed spring session this week, with most MLAs participating by video conference. (Hansard TV)
B.C.’s daily COVID-19 infections dip below 100 over weekend

Only 68 new cases recorded Monday, four additional deaths

Neighbours fight a small late-night bush fire with garden hoses and shovels in Cinnabar Valley on June 5. They couldn’t get help from local fire services because the fire was located in an area under B.C. Wildfire Services jurisdiction. (Photo courtesy Muriel Wells)
Neighbours on edge of Nanaimo city limits left to put out bush fire themselves

Cinnabar Valley residents tackle fire with hoses and buckets for two and a half hours

Darren Campbell’s truck (pictured) was stolen when he stopped to check on a car in a ditch on Cowichan Bay Road on Monday morning. (Facebook photo)
Vancouver Island Good Samaritan’s truck stolen in nasty trick

‘Try to be a Good Samaritan and my $20,000 truck gets stolen right under my nose’

The Kamloops Indian Residential School is photographed using a drone in Kamloops, B.C., Monday, June, 14, 2021. The remains of 215 children were discovered buried near the former school earlier this month. THE CANADIAN PRESS/Jonathan Hayward
Communities grapple with what to do with former residential and day schools

Some tear them down as a tool to help healing, others repurpose them as tools for moving forward

Creative handmade signs abound at the June 13 Tofino rally for old growth trees. (Nora O’Malley photo)
VIDEO: Tofino stands in solidarity for Fairy Creek Blockades

Over 150 supporters attend rally hosted by Friends of Clayoquot Sound

FILE – Provincial health officer Dr. Bonnie Henry talks about B.C.’s plan to restart the province during a press conference at Legislature in Victoria, Tuesday, May 25, 2021. THE CANADIAN PRESS/Chad Hipolito
B.C. watching U.K.’s COVID struggles but don’t think province will see similar pitfalls

Studies show that one dose of vaccine is only 33 per cent effective in preventing B.1.617.2 spread

RCMP Const. Shelby Patton is shown in this undated handout photo. RCMP say that Patton was hit by an allegedly stolen truck that he had pulled over on Saturday morning in Wolseley, east of Regina. THE CANADIAN PRESS/HO, RCMP
Pair charged in Saskatchewan Mountie’s death make first court appearance

Const. Shelby Patton was hit by an allegedly stolen truck that he had pulled over Saturday morning

David and Collet Stephan leave for a break during an appeal hearing in Calgary on Thursday, March 9, 2017. THE CANADIAN PRESS/Todd Korol
Appeal Court rejects stay for Alberta couple facing third trial in son’s death

Pair accused in their earlier trials of not seeking medical attention for their son sooner

Most Read