The Site C dam is proposed for a stretch of the Peace River near Fort St. John

Electricity need key to Site C decision

Review panel not convinced there is enough demand for the $7.9 billion dam project to begin next year

  • May. 8, 2014 8:00 a.m.

An environmental review of BC Hydro’s proposed third dam on the Peace River concludes it offers a long-term source of inexpensive electricity to meet future needs, but panelists are unconvinced that construction needs to start next year.

The joint federal-provincial panel released its report Thursday on Site C, a $7.9 billion project that has been considered for 30 years. Its report describes significant impacts to fish habitat, wetlands and aboriginal hunting and trapping territories, and recommends the B.C. government consider alternatives for clean energy including large-scale geothermal that BC Hydro is currently not allowed to build.

Energy Minister Bill Bennett said the federal and provincial governments will study the 450-page report and decide by this fall whether to issue the required permits. If they are approved, a final investment decision is expected by the end of 2014, with a decade of construction to begin in January 2015.

Bennett noted that the panel did not factor in extra demand for electricity for liquefied natural gas development in northern B.C., because major producers intend to power their LNG processing plants with natural gas.

Bennett said LNG producers will need substantial electricity for their operations, beyond the main machinery for chilling and compressing gas. A smaller LNG plant proposed for the Woodfibre pulp mill site near Squamish would use all-electric processing, and it alone would add substantially to BC Hydro’s industrial load, he said.

“We know the demand for power is growing,” Bennett said. “Our population is set to increase by 1.1 million people over the next 20 years, our economy is growing, people are using more devices and there are new uses for electricity like shore power [for ships in port] and electric vehicles.”

NDP leader John Horgan termed the government’s construction plan “reckless and irresponsible,” adding billions to BC Hydro’s debt at a time when ratepayers are looking at 28% rate increases in the next five years.

Horgan said the uncertainties about load forecasting and costs should be referred to the B.C. Utilities Commission, but Bennett said that is unlikely to happen.

Aboriginal people in the Peace region say Treaty 8 guarantees them the right to hunt, trap and fish as they did before the treaty was signed in 1899.

 

Just Posted

Saanich jam stand at the centre of controversy prepares to close

Staff review of roadside stand legislation too late for Little

Convicted drug trafficker asks Victoria courtroom for chance to ‘turn this around’

Horst Schirmer sentenced for convictions on five counts of possession related to trafficking

$11 million overdraw for McKenzie Interchange construction

The project has been delayed multiple times and is now estimating a budget of $96 million

Alzheimer Society calls for helpline volunteers in Greater Victoria

Charity is in ‘urgent need’ as calls on the rise

Pipeline protestors plan march as Trudeau gives Trans Mountain the go-ahead,

20 kilometre march to protest the pipeline starts in Victoria, ends on Saanich Peninsula

VIDEO: Trans Mountain expansion project gets green light, again

Prime Minister Justin Trudeau announced the decision in Ottawa on Tuesday afternoon

POLL: Do you support the government’s decision to approve the Trans Mountain pipeline expansion?

The federal government announced Tuesday its approval for the Trans Mountain pipeline… Continue reading

Greater Victoria wanted list for the week of June 18

Greater Victoria Crime Stoppers is seeking the public’s help in locating the… Continue reading

Man to be sentenced for sexual abuse of young girl in Nanaimo

Stephen Mark Castleden also sentenced for child pornography-related charges

MPs hear retired B.C. nurse’s petition to change compensation for fatal medical errors

Teri McGrath wants provinces to implement no-fault system for medical errors

Horgan says he’ll still defend B.C. coast after second Trans Mountain approval

Meanwhile, one B.C. First Nation has announced plans for a legal challenge

VIDEO: Firefighters stop blaze from spreading after BMW crashes at Saratoga Speedway

Victoria-based businessmen were ‘corner training’ on Father’s Day when incident took place

Demonstrators on either side of Trans Mountain debate clash in Vancouver

Crowd heard from member of Indigenous-led coalition that hopes to buy 51% of expansion project

Grieving B.C. mom hopes Facebook message leads to new investigation into son’s Surrey homicide

Criminal Justice Branch didn’t lay charges, concluding no substantial likelihood of murder or manslaughter conviction

Most Read