Natural Gas Minister Rich Coleman (left) and Premier Christy Clark tour PETRONAS natural gas import terminal in Malaysia in May.

Prince Rupert LNG plant, pipelines get B.C. certificates

PETRONAS aiming for investment decision by the end of this year, Nisga'a Nation on board with $11 billion development plan

Provincial environmental assessment certificates have been approved for B.C.’s flagship liquefied natural gas export project at the Port of Prince Rupert and two pipelines proposed to connect the region to gas fields in northeastern B.C. to the North Coast.

The $11.4 billion project led by the Malaysian state-owned energy corporation PETRONAS is aiming to make its final investment decision by the end of this year. One of the certificates issued is for the Prince Rupert Gas Transmission pipeline, proposed to run 900 km from Hudson’s Hope to the PETRONAS Pacific NorthWest LNG terminal.

The LNG port and pipelines must still receive federal, provincial and local government permits before they can begin construction. The Pacific NorthWest LNG terminal at Lelu Island is still undergoing federal environment assessment, having received an extension to deal with potential salmon habitat impacts at the mouth of the Skeena River.

Natural Gas Development Minister Rich Coleman visited Malaysia this month at the invitation of PETRONAS officials to go over their project.

PETRONAS is leading a consortium that includes Chinese, Japanese, Indian and Brunei investors for a pipeline and LNG processing in northern B.C. PETRONAS paid $5 billion last year to take over Progress Energy Canada, which has major shale gas holdings in northeast B.C. and Alberta.

Pacific NorthWest LNG received another boost last week when the Nisga’a Nation signed a benefits agreement with the B.C. government for the project. The B.C. and Nisga’a legislatures are passing amendments to allow the Prince Rupert Gas Transmission pipeline to pass through Nisga’a Memorial Lava Bed Park.

The other certificate is for the Westcoast Connector Gas Transmission pipeline proposed to run from the Fort St. John area to another LNG terminal at Ridley Island. That project is led by BG Group, which has signalled it may delay development because of new gas supplies from U.S. sites where the British-based company also has LNG export plans.

 

Just Posted

Project provides barrier to suicides at hospital parkade

VIHA budgets $650,000 for work at Royal Jubilee Hospital parkade

Pandora supervised consumption site has busy first month

Site whose aim is to save lives takes on a new client-driven name: The Harbour

Victoria’s plastic bag ban inspires local entrepreneur to give back

Karebags a local, collaborative alternative for reusable bags, donates profits to charity

BC Nurses Union calls for decriminalization of opioids

BCNU president wants the federal government to do more to reduce preventable deaths

Pedestrian struck on Quadra Street

A pedestrian was struck by a vehicle on Quadra Street at Hulford… Continue reading

VIDEO: Trudeau shuffles familiar faces, adds new ones to expanded cabinet

Justin Trudeau shuffles his front bench Wednesday to install the roster of ministers that will be entrusted with leading the Liberal team into next year’s election.

Greater Victoria prices continue to rise as market shows signs of cooling

A survey shows the aggregate price of a home in Victoria increased… Continue reading

B.C. hockey coach, nurse was killed in case of mistaken identity, police say

In Surrey, Paul Bennett’s wife makes a tearful plea for help in finding her husband’s killer

Lower Mainland blueberry farms expect solid season

Blueberry Council of B.C. says season will be better than last year

B.C. to add hundreds of taxis, delays Uber, Lyft-style service again

Ride hailing companies have to wait until fall of 2019 to apply for licences

BC Games ready to begin on Vancouver Island

More than 2,000 athletes will compete in 18 sports from Friday to Sunday

Plenty of heroes in Thai cave rescue, says B.C. diver

Erik Brown reflects on team effort that brought 12 boys and their coach to safety

Funding available to replace infected B.C. hazelnut trees

B.C. Hazelnut Growers to recieve $300,000 over three years to battle eastern filbert blight

Woman charged after eight dogs seized from hotel room

Sixteen dogs recently seized from Adams and her daughter in Quesnel

Most Read