Undersea cable pitched for clean energy

A company known mostly for wind projects is reviving a proposal to connect the Vancouver Island and Washington electricity grids

Wind farm development in northeastern B.C. Proponents of a new power line between Vancouver Island and Washington say it would make wind power a more stable source.

VICTORIA – With BC Hydro struggling to control electricity rate increases and cutting back on private power acquisition, a company known mostly for wind projects is reviving a proposal to connect the Vancouver Island and Washington electricity grids.

Sea Breeze Power Corp. wants to build a 50 km transmission cable under the Strait of Juan de Fuca to connect substations near Port Angeles and Victoria. To finance the project, it’s looking for a 10-year deal to assemble surplus U.S. power and sell it to BC Hydro at a flat rate of $69 per megawatt hour.

Sea Breeze CEO Paul Manson said the power purchase would finance the construction of the cable and deliver a steady source of electricity to B.C. at lower cost than new sources built in the province. It would also improve power quality and reliability for Vancouver Island residents, he said.

First proposed in 2006, the project has received environmental permits from both sides of the border. It was rejected by the B.C. Utilities Commission, which approved upgrading the existing power line from the B.C. mainland to Vancouver Island instead.

Sea Breeze developed a wind project at Cape Scott on northern Vancouver Island, and has plans and permits for other wind sites on the B.C. coast and the Peace River region. Manson said the Juan de Fuca cable would stabilize wind power supply on the B.C. coast, where wind speeds peak in winter, with inland Washington sites where it’s windiest in summer.

Manson said U.S. policy led to major wind development that leaves the the Pacific Northwest with an excess of power in spring, meaning the Washington power utility has paid BC Hydro to take its excess when hydro dams are full.

The cable would also give B.C. more capacity to buy cheap overnight coal and nuclear power from the U.S., which BC Hydro already does with its main connecting line along Interstate 5, he said.

Energy Minister Bill Bennett said the Juan de Fuca cable is one of many proposals that came forward as BC Hydro developed its integrated resource plan. That plan estimates that with conservation and efficiency improvements in B.C., the province will need more electricity supplies within eight years.

The company has not yet demonstrated that it can assemble the firm electricity it proposes to sell, and the project has “a pretty steep slope to climb,” Bennett said.

 

Just Posted

Pearkes book sale will have 15,000 titles

Some seek volume of books while others hunt early editions in annual Saanich sale

Gingerbread Showcase returns for another year of delicious fun in Victoria

Funds raised from the event support Habitat for Humanity Victoria’s build in Central Saanich

Lavigne steps Under the Mistletoe in Victoria to kick off holiday season

Under the Mistletoe is on Tuesday, Dec. 4 at the Royal Theatre

Temperature records broken in Esquimalt Harbour and four other B.C. cities

The last temperature record in Esquimalt Harbour was set in 1999

Unique technology gives children with special needs more independent play

UVic’s CanAssist refined seven prototypes aided by $1.5M government contribution

Greater Victoria holiday craft fair roundup for Nov. 16 to 18

Check off all of the items on your shopping list at these great events

Greater Victoria Crime Stoppers wanted list for the week of Nov. 14

Greater Victoria Crime Stoppers is seeking the public’s help in locating the… Continue reading

B.C. teacher’s Amazing Race takes students on Canada-wide adventure

Agassiz high school students say they had the experience of a life time

Don’t sign USMCA until LGBTQ language excised, U.S. lawmakers urge Trump

The trade agreement, forged after 13 months of tense negotiations between Canada and the U.S. is scheduled for Nov. 30

US official: US intel says prince ordered Khashoggi killing

Vice-President Mike Pence told reporters that ‘the murder of Jamal Khashoggi was an atrocity.’

Canada’s health system commendable overall but barriers to care remain: UN

The United Nations says Canada’s health care system is “commendable” overall but vulnerable groups still face barriers to quality care.

Road rescue near Sayward points to volunteer need

Fire department recruits can be tough for small, remote communities

Most Read