McKenzie interchange construction delayed into summer 2019

Completion date has been delayed to Summer of 2019, with some work to continue until 2020.

Keep cool Colwood crawlers, as construction for the McKenzie interchange project will take an extra seven months.

The Ministry of Transportation and Infrastructure confirmed the project is now on track for a summer 2019 completion, at least seven months longer than the fall 2018 target date.

Jacob Bros. ran into surprise winter conditions of heavy rain and snow that delayed settling of the fill materials (rock, dirt and gravel).

“The ministry adjusted the schedule to lessen both traffic and noise impacts and to improve traffic flow along the corridor to better accommodate the needs of nearby residents,” said a MOTI statement on Thursday. “As well, there were challenging weather conditions this past winter requiring more time for the ground to settle for the subsequent construction in Phase 1.”

RELATED: First phase of McKenzie interchange work at halfway point

Wednesday’s announcement from MOTI confirmed Westpro Constructors will lead the second and final construction contract for the project, a $42.6-million contract and will pick up where Jacob Bros. leaves off.

“Jacob Bros. did excellent work on Phase 1 and will now work to complete their contract and Westpro will being Phase 2 work early October 2017.”

RELATED: Contractor sends raw sewage into Saanich streets.

The remaining work involves lowering the Trans-Canada Highway underneath McKenzie-Admirals, constructing the ramps, overpass, and new pedestrian-cyclist bridge over the highway.

RELATED: Government commits to McKenzie interchange project

RELATED: Province won’t reverse course on interchange

Westpro is based out of the Lower Mainland where they have led similar projects such as the McCallum Road bridge and interchange with Highway 1 in Abbotsford, and four of the 12 Millenium Line Skytrain stations (Sperling/Burnaby Lake, Lake City Way, Production Way/University, and Braid Station).

“A tremendous amount of progress can be seen on-site and awarding the second contract is another milestone step towards completing this interchange project that will improve traffic flow in the Capital Regional District, reduce collisions, and improve safety for pedestrians and cyclists,” said new Transportation and Infrastructure Minister Claire Trevena.

RELATED: Park patron see highway berm as threat to Colquitz

RELATED: Road construction has residents losing sleep

Other construction delays have picked up in recent months though the most disruptive tasks have been done outside of peak traffic periods, usually overnight.

Follow www.drivebc.ca for traffic updates.

The total estimated cost of the Highway 1 Admirals Road/McKenzie interchange is $85 million, with the Government of Canada contributing up to $32,647,500 under the New Building Canada Fund’s Provincial-Territorial Infrastructure Component-National and Regional Projects and the Government of British Columbia funding the remaining $52,352,500.

reporter@saanichnews.com

Get local stories you won't find anywhere else right to your inbox.
Sign up here

 

Construction on the $85 McKenzie interchange project will enter the second and final phase this fall. (Black Press file photo)

Just Posted

PHOTOS: Hundreds celebrate Year of the Rat in Victoria’s Chinatown

Lion dancers and kung fu demonstrations on display

Camosun student shares story of overcoming struggles to inspire others

Provincial Tuition Waiver Program helps former youths in care attend post-secondary institutions

Officials reaching out to those in contact with Canada’s first coronavirus patient

The illness has sickened at least 1,975 people and killed 56 in China

Canada’s basketball community mourns Kobe Bryant after helicopter crash

Bryant was an 18-time NBA all-star who won five championships

‘Devastated’: Fans, celebrities remember Kobe Bryant after his death

Bryant played all of his 20-year career with the NBA with the Los Angeles Lakers

Investigation launched after six dead puppies dumped in Richmond hotel parking lot

RAPS reminds people they can always give up puppies they can’t take care of

Canadian Lunar New Year celebrations dampened by coronavirus worries

But Health Minister Patty Hajdu said today that the risk of infection is low

B.C. VIEWS: New coronavirus outbreak an important reminder

Walking the line between cautious and alarmist

Kobe Bryant, daughter killed in California helicopter crash

Bryant entered the NBA draft straight out of high school in 1996

Risk of coronavirus low in B.C. as first case emerges in Toronto: officials

There have been no confirmed cases of the virus in B.C.

Most Read